Settlement monitoring of two new silos with connecting tunnel

MONITORING AND SETTLEMENT MONITORING 

At the cement plant operated by Austrian company Schretter & Cie GmbH & Co KG, based in Vils, an automated monitoring system from GLÖTZL was installed to measure the settlements of two newly constructed silos during their initial filling phase.
In addition to the two silos, the monitoring concept also includes the underground connecting tunnel.

Project: Construction of two new clinker silos and connecting tunnel
Start of construction: 2025
Client: Schretter & Cie GmbH & Co KG, Vils, Austria
(Image copyright: Schretter & Cie)
Special features: Settlement monitoring with online access via SDC and active monitoring management
GLÖTZL instrumentation: Hydraulic settlement gauges GHD3 (12 units in the tunnel, 2×4 units on the silos, 2 reference points on 2 levels), Data acquisition system MCC,  Software: GLA and SDC, Online access enabled

Smart Data Center SDC: Settlement monitoring of the connecting tunnel
Smart Data Center SDC: Settlement measurements of new silos